Shopping Mall Programme

D
Dean Jones 👤 Member for 16 years 10 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Dean,



I recommend that you divide the project into:



Main Building

Annexes; Sewage Treatment Plant, Water Treament Plant

Landscape Works.



The Main Building is the Critical of course. I assume that you have several basements. Once you finish you 2nd basement from the bottom, your 1st basement formwork will be removed, and you can start your EM activities. The EM activities in the public areas will stay up to the end. Usually you have the space open for rent and the Tenants will do the EM works themselves. All you have to do is bring the networks up to their connection points.



EM Activities can goin parallel, but usuall you have:



1. HVAC works; marking, support system, ducting, testing, insulation.

2. Fire Fighting works: marking, support system, ducting, testing, insulation.

3. Plumbing

4. LPG



Electrial works must start with the Cable Trays, then you install the main cables and at last you do the termination of the Main Electrical Panels (Power, lightin, low current).



Once you complete the Main Building structure, you can start with the Facade works.



The bounday walls you can start at your earliest. It will give you site security and you will save up on the fencing.



The people movers (escalators, etc) are long lead items. So you must get approval and order them within max 3 months period.



The signage will not be clear until the mall is rented out and that is at the last stages.



Hope that the information helps.



With kind regards,



Samer

D
Dean Jones 👤 Member for 16 years 10 months

Thanks for all the replies.

here is my set of activities, which has to be completed in around 24 months time.

Civil work (Structure) 12 months

Building finishes 12 months

Facade- Glazing

Cornices external finishes

Landscapping

External works like Boundary walls and roads

Plumbing

Signage

Car parking management system

Gas bank

Public address system

Escalators & lifts.

Electrical

Firefighting

Sewage Treat Plant

Water Treat Plant

DG sets

HSD tanks for DG

AC includes

Access control system

CCTV

BMS

lighting arrangement inside and external lighting.



Can someone guide me which MEP activity can go parallel and with what activity.

what kinda relationship that can be established from the given set of details.



kindly guide me.


R
Rashid Iqbal 👤 Member for 16 years 2 months



Before you start open up the project estimate, get an idea what there CBS is ..map there CBS to project WBS and the details that Samer has provided.



It will give you most of the details that you are looking for..including details for resource loading the schedule. Thanks.




S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Dean,



How about if we write it up here. It will take up 1-2 days from your time.



The is level 1:



Excavation

Skeleton Works and E/M first fix

Electromechanical Works

Finishing Works

Cladding

Fit up period for tenants.

Kitchens

Toilets

Elevators and Escalators and people movers

Metal Works

Wood Works

Water features

Landscaping

Signage



Give us a bit more idea about your project, and we can give you more details about what is needed to be accomplished. This will enable you to complete your Program in no time.



With kind regards,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

Hi



In addition to Samer’s post ,add WBS for Testing & Commissioning

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts