Hi Gray
I have come across a case in which the specification states that delivery of materials Eg,-Generator ,at site cost 75% of Budgeted Value and remaining 25 % goes to the respective installation Activities
Hi Gray
Are u looking for Earned Value procedure in MEP or WBS in developing the MEP Baseline schedule
Im looking for how you apportion the budget cost & assocaited earned value of major M&E kit in your baseline programme
e.g. perhaps 10% of the value is earned when the order is placed, 50% throughout manufacturing period, 10% at FAT and 30% on delivery