Planned schedule % using late

J
jeoffrey reyes 👤 Member for 17 years 11 months

Hi Rodel & Vellu,



Sorry for this remark, but I think Vellu wanted to show late percentage because of huge variance in Actual.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vellu,

I’m not sure what you are trying to do. Remaining Late means it not yet happen or late forecast so how can you compare it with Actual which already happened?



It is possible to compare Early and Late but not actual and late.

Note: Scheduled or planned is baseline which is already set and actual is physical effort recorded.

V
vellu shanmugam 👤 Member for 16 years 6 months

Dear Rodel,



If I intend to use the cost loaded remaining late units for my schedule % (planned %), is it possible?



Eg. Schedule % : 43% (can I use the late units to show

in P6.)

Actual % : 32%

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vellu,

Remaining Early Units and Remaining Late Units are available at Resource usage spreadsheet (cost loaded or not) as long as you have resources assigned.

V
vellu shanmugam 👤 Member for 16 years 6 months

How about if i want to use the late units as my planned schedule % instead of using early units.





Correct me if wrong; to show the planned schedule % i need to cost loaded right?. But this will only use the early units.

Can it use fo late units too?


N
niles luo 👤 Member for 20 years 6 months

hi,

In the activity usage spreedsheet window,the field of late resource units can be selected to display.

Best Regards

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts