Hi Rodel & Vellu,
Sorry for this remark, but I think Vellu wanted to show late percentage because of huge variance in Actual.
Vellu,
Im not sure what you are trying to do. Remaining Late means it not yet happen or late forecast so how can you compare it with Actual which already happened?
It is possible to compare Early and Late but not actual and late.
Note: Scheduled or planned is baseline which is already set and actual is physical effort recorded.
Dear Rodel,
If I intend to use the cost loaded remaining late units for my schedule % (planned %), is it possible?
Eg. Schedule % : 43% (can I use the late units to show
in P6.)
Actual % : 32%
Vellu,
Remaining Early Units and Remaining Late Units are available at Resource usage spreadsheet (cost loaded or not) as long as you have resources assigned.
How about if i want to use the late units as my planned schedule % instead of using early units.
Correct me if wrong; to show the planned schedule % i need to cost loaded right?. But this will only use the early units.
Can it use fo late units too?
hi,
In the activity usage spreedsheet window,the field of late resource units can be selected to display.
Best Regards