P3e Baselines

H
Henk van der Heide 👤 Member for 21 years 11 months

Hi,



Yes indeed the function of Target update is missing. But maybe this helps a little bit.

If you restore the baseline as a project an open the formal baseline and the current project you wil be able to sort (or organize) on activity ID. What you get is current and baseline activity grouped together so its easier tot compare (the difference)




S
Shirish Borkar 👤 Member for 21 years 7 months

As a workaround you can delete and recreate the baseline assuming you have not changed other activity data.



And if that feature is very important to you, you can develop it using Primavera Ingration API.

A
Alan Chadwick 👤 Member for 23 years

Cheers Allan,



So the bottom line appears to be that a very important function/feature does not have much flexibility.

A
Allan Stanners 👤 Member for 23 years 2 months

This is a known issue in the current version of P3e. I understand it will be rectified in V 5.0 due for release in 1st quarter 2005. This will allow the same functionality that exists in P3 to update the baseline as new tasks are added.

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts