Oracle P7 admin or user setting,
Forum Sponsor
Top Posters
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
Shazia,
You can use either Global or Project Calendar for activities but must select Global Default calendar.
Thanks so much for your prompt reply.
i have to use project cal or Global Cal.
I made Project cal for 5dys and 6 days.
Please clear .
Thanks
Shazia,
In P6v7 new settings is Admin-> Admin Preferences-> Time Period tab.
The Previous options of Allow users to edit hours per time period are now change to allow calendar settings for hours per time period.
If this option is selected, any assigned calendar will used calculating activity durations and Global Default calendar will be used for summary.