Oracle P7 admin or user setting,

S
Shazia khan 👤 Member for 18 years 1 month
R
Rodel Marasigan 👤 Member for 19 years 7 months

Shazia,

You can use either Global or Project Calendar for activities but must select Global Default calendar.

S
Shazia khan 👤 Member for 18 years 1 month

Thanks so much for your prompt reply.



i have to use project cal or Global Cal.



I made Project cal for 5dys and 6 days.



Please clear .



Thanks

R
Rodel Marasigan 👤 Member for 19 years 7 months

Shazia,

In P6v7 new settings is Admin-> Admin Preferences-> Time Period tab.

The Previous options of Allow users to edit hours per time period are now change to allow calendar settings for hours per time period.

If this option is selected, any assigned calendar will used calculating activity durations and Global Default calendar will be used for summary.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts