Show number of resoures in activity column

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vaughn,

Sorry for misunderstanding as you mentioned columns and not label. If label you wanted as per Roger advise use UDF and populate using Global Change then assigned to a bar. You can always run Global Change to update if resources change.



Hope this help.

V
Vaughn Edwards 👤 Member for 18 years 1 month

I understand how to get Budgeted Unit/Time to appear in the Activity and Resource windows, what I’m looking to do is see a column in the Gantt view of the number of resources assigned to that activity.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vaughn,

If using Resource Window, right click and select columns-> Customize.

Under General you can select Budget Unit/Time and Remaining Unit/Time.



If using Activity Window select Resources tab. Right click on Resources table and select Customize Resource Columns. Under General select Budget Unit/Time and Remaining Unit/Time.

R
Roger Booth 👤 Member for 19 years 7 months

I use one of the user defined fields and then attach that UDF to the bar. Gives you a display very similar to dare I say Microsoft Project

V
Vaughn Edwards 👤 Member for 18 years 1 month

Thanks for your reply. I have found the number of resources under the resource and activity windows, but the budgeted Unit/Time isn’t available to choose to inset a column. Thats my problem.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Vaugh,

It is now on Resource Window (P3 don’t have before) and called Budgeted Unit/Time for Budget units and Remaining Unit/Time for Remaining Unit. It is also available on Activity Window Detail-> Resource tab.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts