How to Set up cut-off date in P3

A
Angel Cruz 👤 Member for 16 years 2 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Anbin,

you are right, I was confusing with the "New project" window; your solution is the best one, of course

Alexandre

A
Anbin Ponnith 👤 Member for 17 years 1 month

Dear Angel Cruz,

I find another Option also which is very easy

Data->Calender->Click Global Calender->Standard->Week start on -> Change to Saturday

I tried it Just Now it Work

Regards

Anbin

A
Anbin Ponnith 👤 Member for 17 years 1 month

Dear Alexandre,



I tried your solution but could not find any option to change the 1st day of the week to Saturday..



Could you please expain me in detail.





With Thanks & Regards,



Anbin Ponnith

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hi Angel and Anbin,

I guess it would be easier to use Tools, Project Utilities, Copy, and copy the current project to a new one in which the 1st day of week is Saturday

You would not have to copy the data dictionary, as P3 would do it automatically

Alexandre

A
Anbin Ponnith 👤 Member for 17 years 1 month

Hai Angel Cruz

U try the Following Option

1.First Create a new Project(ABC)in that give Week start on Saturday

2.Open your Current Project Select all Activities

3.Click Tools->Fragnet->Store Fragnet->Type Id->Type Title

4.Open the New Project (ABC)Transfer all the Dictonary Like

a.Activity code

b.Resource

c.WBS

5.Tools ->Fragnet->Restore Fragnet->Select Correct ID u Typed Before

6.Select Rename Duplicate Only -> OK

7.Now u Can see the New Project Similar to the Current Project

8.Now U can Try Tabular Report

I Hope it works

Regards

Anbin

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts