How to Set up cut-off date in P3
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Tnx to all i got it. This forum is amazing...
Anbin,
you are right, I was confusing with the "New project" window; your solution is the best one, of course
Alexandre
Dear Angel Cruz,
I find another Option also which is very easy
Data->Calender->Click Global Calender->Standard->Week start on -> Change to Saturday
I tried it Just Now it Work
Regards
Anbin
Dear Alexandre,
I tried your solution but could not find any option to change the 1st day of the week to Saturday..
Could you please expain me in detail.
With Thanks & Regards,
Anbin Ponnith
Hi Angel and Anbin,
I guess it would be easier to use Tools, Project Utilities, Copy, and copy the current project to a new one in which the 1st day of week is Saturday
You would not have to copy the data dictionary, as P3 would do it automatically
Alexandre
Hai Angel Cruz
U try the Following Option
1.First Create a new Project(ABC)in that give Week start on Saturday
2.Open your Current Project Select all Activities
3.Click Tools->Fragnet->Store Fragnet->Type Id->Type Title
4.Open the New Project (ABC)Transfer all the Dictonary Like
a.Activity code
b.Resource
c.WBS
5.Tools ->Fragnet->Restore Fragnet->Select Correct ID u Typed Before
6.Select Rename Duplicate Only -> OK
7.Now u Can see the New Project Similar to the Current Project
8.Now U can Try Tabular Report
I Hope it works
Regards
Anbin