Reason for the change FF>TF?

S
Shah. HB 👤 Member for 17 years 7 months
S
Shah. HB 👤 Member for 17 years 7 months



Many thanks Umar & Anwar



I got the solution for the raised query

U
Umer Mehmood 👤 Member for 18 years

some times in this problem happen when you changed your calculation mode preference , especially when open ended activities are consider critical while scheduling



Hope this will help



Best REGARDS



UMER MEHMOOD

ABU DHABI

M
muhammad anwar 👤 Member for 19 years 4 months

Shahul,



If there is a must finish by constraint or mandatory finish pushing end earlier than what it should be will result in FF>TF. Check for the contraints and project finish date at project setting level.



Hope this will solve the problem.



regards



Muhammad

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts