Reason for the change FF>TF?

S
Shah. HB 👤 Member for 17 years 6 months
S
Shah. HB 👤 Member for 17 years 6 months



Many thanks Umar & Anwar



I got the solution for the raised query

U
Umer Mehmood 👤 Member for 17 years 11 months

some times in this problem happen when you changed your calculation mode preference , especially when open ended activities are consider critical while scheduling



Hope this will help



Best REGARDS



UMER MEHMOOD

ABU DHABI

M
muhammad anwar 👤 Member for 19 years 4 months

Shahul,



If there is a must finish by constraint or mandatory finish pushing end earlier than what it should be will result in FF>TF. Check for the contraints and project finish date at project setting level.



Hope this will solve the problem.



regards



Muhammad

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts