Many thanks Umar & Anwar
I got the solution for the raised query
some times in this problem happen when you changed your calculation mode preference , especially when open ended activities are consider critical while scheduling
Hope this will help
Best REGARDS
UMER MEHMOOD
ABU DHABI
Shahul,
If there is a must finish by constraint or mandatory finish pushing end earlier than what it should be will result in FF>TF. Check for the contraints and project finish date at project setting level.
Hope this will solve the problem.
regards
Muhammad