Hi
This is ok, But u can do Every month wise schedule take % that is Planned %
This one method this not correct method also
Any one guide me how to take the planned % (Proper way)
Ok thanks
Jaq
Dear Anbin
This pont I didnot get u.....
Please define me little deailed ???
Regards
Arun V
Hai Arun
If ur Program is not Cost Loaded u can track Planned Vs Actual Based on Duration
In order to Get Month Planned% u can try the following Steps
1.Check Duration Type- Fixed duration&Units, Percentage Complete-Duration
2.Copy Ur Program & Paste it.
3.Tools - Update Progress-Select The Date(Show Time also)
4.Press F9 - Select The Date(Same Date what u gave in Update Progress)
5.Schedule it
6.Note Down Schedule% For the Corresponding month
7.Repeat the Step 2,3,4 for the other month
8.Schedule% is calculated based on formula
(OD-RD/OD)*100 OD-Orginal Duration
RD-Remining Duration
I hope it might work for as its not resorce loaded
if Not Rodel Can Help You