Over all Project Planned % VS Actual Percentage

A
A.Jaffer Sadiq 👤 Member for 17 years 8 months

Hi



This is ok, But u can do Every month wise schedule take % that is Planned %



This one method this not correct method also



Any one guide me how to take the planned % (Proper way)



Ok thanks



Jaq

A
Arun Vasanth 👤 Member for 16 years 8 months

Dear Anbin



This pont I didnot get u.....



Please define me little deailed ???

Regards

Arun V

A
Anbin Ponnith 👤 Member for 17 years

Hai Arun

If ur Program is not Cost Loaded u can track Planned Vs Actual Based on Duration

In order to Get Month Planned% u can try the following Steps

1.Check Duration Type- Fixed duration&Units, Percentage Complete-Duration

2.Copy Ur Program & Paste it.

3.Tools - Update Progress-Select The Date(Show Time also)

4.Press F9 - Select The Date(Same Date what u gave in Update Progress)

5.Schedule it

6.Note Down Schedule% For the Corresponding month

7.Repeat the Step 2,3,4 for the other month

8.Schedule% is calculated based on formula

(OD-RD/OD)*100 OD-Orginal Duration

RD-Remining Duration

I hope it might work for as its not resorce loaded

if Not Rodel Can Help You

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts