ok thanks Mr.Rodel
ok thanks
Bhushan,
Project finish date is not editable. It is the result of logic assigned to activities. You can forced finish date by adding mandatory finish constraint on the last activity but it will gave you wrong float calculation and not advisable.
Thanks , also can a project finish date can be removed for must finish date
Bhushan,
Your thread title is Dates Constrains and that how I interpret it. Maybe you are looking for Project Window detail-> Date Tab and under Schedule dates change Project Planned Start & Must Finish date.
I mean how to change project start dates and finish dates for project
Bhushan
Naga Bhushan Jangam,
Activity Window Detail-> Status tab. You should find Constraints section: Primary and Secondary and change the constrain type that you wanted.