Dates Constraints

R
Rodel Marasigan 👤 Member for 19 years 8 months

Bhushan,

Project finish date is not editable. It is the result of logic assigned to activities. You can forced finish date by adding mandatory finish constraint on the last activity but it will gave you wrong float calculation and not advisable.

R
Rodel Marasigan 👤 Member for 19 years 8 months

Bhushan,

Your thread title is Dates Constrains and that how I interpret it. Maybe you are looking for Project Window detail-> Date Tab and under Schedule dates change Project Planned Start & Must Finish date.

R
Rodel Marasigan 👤 Member for 19 years 8 months

Naga Bhushan Jangam,

Activity Window Detail-> Status tab. You should find Constraints section: Primary and Secondary and change the constrain type that you wanted.

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts