Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Thu, 2010-06-17 03:18
Member for
19 yearsRE: Calculating Hours-Man with Project
Jhorbam,
Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.
Member for
19 years 11 monthsRE: Calculating Hours-Man with Project
Remaining Work?
See the Work Table.