Calculating Hours-Man with Project

R
Rodel Marasigan 👤 Member for 19 years 9 months

Jhorbam,

Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.