Our team has run into an issue with negative float being calculated to a Level of Effort task. Background: We work in a very large Integrated Master Schedule (IMS) that encompasses in excess of 30 individual projects. These projects have multiple tasks that are logically linked from one project to another.
The current issue: I have a LOE that only has a SS relationship to a task within that project (with 0 Days Total Float) and a FF relationship to another task within that project (with 232 Days Total Float). The problem is that the LOE indicates -620 Days Total Float. There are no constraints (Start On or After, Finish On or After, etc.) assigned. I must be missing something?
I understand that Sunday is working day in Middle East but your Global default calendar has Sunday working too?
You need to advise your consultant to change the Global default calendar and hours per time period to match the activity calendar. That will give them the correct duration value.
We have sunday as working days in Middleeast that is not a problem.....
I am facing a big problem in this program, whenever i give a program to the Consultant with Must Finish date of 24th July 2011 , but when consultant is scheduling my program he is getting a 7 days delay...i.e. showing completion date as 31st July 2011....Why i check & schedule my program and then i given to the consultant for review...
But why does the same program when opened on his system is showing a different finish dates with delay......
24 July 2011 is Sunday therefore it will shift to either following day or before depends on your calendar working day. If the finished is on summary band then change the Global Default calendar to match activity calendar. Also change Hours time period to match working hours. That is always the source of problem when Global default is not matching activity calendar and working hours is not matching Hour per time period.
My problem is that the must finish date is fixed as 24th July 2011 7:00 pm, but whereas Project Handing date is showing as 25th July 2011 10:00 am with Zero total float.
I can understand, the program logic if my project handing over date shows 25th July 2011, with one day negative float. But in my program it shows Zero float eventhough my must finish date is fixed as 24th Juy 2011. Can u explain this ....if u are not able to get it i can send my program for ur review....
Must Finish date is not constraining Activity. It is used to calculate the schedule on "Backward pass" to show the float whether negative or positive. If Must finish date is less than current project finish date then some critical activities will be showing negative float but if current project finish date is less than must finish date then it will show all positive float.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Our team has run into an issue with negative float being calculated to a Level of Effort task. Background: We work in a very large Integrated Master Schedule (IMS) that encompasses in excess of 30 individual projects. These projects have multiple tasks that are logically linked from one project to another.
The current issue: I have a LOE that only has a SS relationship to a task within that project (with 0 Days Total Float) and a FF relationship to another task within that project (with 232 Days Total Float). The problem is that the LOE indicates -620 Days Total Float. There are no constraints (Start On or After, Finish On or After, etc.) assigned. I must be missing something?
Haresh,
I understand that Sunday is working day in Middle East but your Global default calendar has Sunday working too?
You need to advise your consultant to change the Global default calendar and hours per time period to match the activity calendar. That will give them the correct duration value.
Dear Rodel,
We have sunday as working days in Middleeast that is not a problem.....
I am facing a big problem in this program, whenever i give a program to the Consultant with Must Finish date of 24th July 2011 , but when consultant is scheduling my program he is getting a 7 days delay...i.e. showing completion date as 31st July 2011....Why i check & schedule my program and then i given to the consultant for review...
But why does the same program when opened on his system is showing a different finish dates with delay......
regards,
Haresh Jayanth
Haresh,
24 July 2011 is Sunday therefore it will shift to either following day or before depends on your calendar working day. If the finished is on summary band then change the Global Default calendar to match activity calendar. Also change Hours time period to match working hours. That is always the source of problem when Global default is not matching activity calendar and working hours is not matching Hour per time period.
This happens to me as well sometimes...what i do is assigning lag -1(FF Activity of LOE), though its not the right way to do.
Dear Rodel,
My problem is that the must finish date is fixed as 24th July 2011 7:00 pm, but whereas Project Handing date is showing as 25th July 2011 10:00 am with Zero total float.
I can understand, the program logic if my project handing over date shows 25th July 2011, with one day negative float. But in my program it shows Zero float eventhough my must finish date is fixed as 24th Juy 2011. Can u explain this ....if u are not able to get it i can send my program for ur review....
regards,
Haresh
Haresh,
Must Finish date is not constraining Activity. It is used to calculate the schedule on "Backward pass" to show the float whether negative or positive. If Must finish date is less than current project finish date then some critical activities will be showing negative float but if current project finish date is less than must finish date then it will show all positive float.