Duration in WBS Band not reflect total Project Duration
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Haresh,
Click the link below where I explained how the calendar works in P6.
Multiple calendar scheduling Post#3
Haresh
1. The Start and Finish dates of the black summary band representing the entire time the activities are working is calculated from the earliest Start date of all included activities to the
latest Finish date of all included activities.
2. The amount of available work hours between the start and finish dates of the summary band is calculated using the Global default calendar.
3. The total number of available work hours defined on the global default calendar is divided by the hours/day setting found in Admin, Admin Preferences, Time Periods to determine
the duration in days of the summary band.
regards
Dear Samer,
I very well know that , the WBS summary does not has time associated with it , my question was , why doesnt it reflects the correct duration of the project??
regards,
Haresh Jayanth
Dear Haresh,
It has to do with the View that you are using. WBS has no time associated with it.
With kind regards,
Samer