Duration in WBS Band not reflect total Project Duration

M
muhammad anwar 👤 Member for 19 years 4 months

Haresh



1. The Start and Finish dates of the black summary band representing the entire time the activities are working is calculated from the earliest Start date of all included activities to the

latest Finish date of all included activities.

2. The amount of available work hours between the start and finish dates of the summary band is calculated using the Global default calendar.

3. The total number of available work hours defined on the global default calendar is divided by the hours/day setting found in Admin, Admin Preferences, Time Periods to determine

the duration in days of the summary band.





regards


H
Haresh Jayanth 👤 Member for 19 years 9 months

Dear Samer,



I very well know that , the WBS summary does not has time associated with it , my question was , why doesn’t it reflects the correct duration of the project??



regards,



Haresh Jayanth

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Haresh,



It has to do with the View that you are using. WBS has no time associated with it.



With kind regards,



Samer

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts