Importing from P3 to MSP

C
Carlos Arana 👤 Member for 17 years 1 month

Thanks Rodel, But I have a P3 database to start with and want to convert it to MS Project.



Best regards,

Carlos.

R
Rodel Marasigan 👤 Member for 19 years 9 months

Carlos,

Check your MSP and the link maybe on Summary Task and check Project Information and make sure it has the correct data date before converting to MPX then convert to P3. (Note Higher version of MSP doesn’t convert MPX only MSP 98 and below)