Thanks Rodel, But I have a P3 database to start with and want to convert it to MS Project.



Best regards,

Carlos.

Member for

19 years

Carlos,

Check your MSP and the link maybe on Summary Task and check Project Information and make sure it has the correct data date before converting to MPX then convert to P3. (Note Higher version of MSP doesn’t convert MPX only MSP 98 and below)