WBS Milestone Weightage

Member for

19 years

Haresh,

That is wrong. Est Weight is used by Top Down Estimation. If you put Est Weight at Activity or WBS and use Top Down Estimation, the units or costs will be distributed according to est weight that specified on Activity or WBS.



For Earned Value using WBS Milestone Percent Complete is to create a Milestone Step which is similar to activity steps.

Milestone Step or WBS Milestone is under WBS Window-> WBS Milestone tab.

Planner needs to create a WBS Milestone step and EV will be calculated according to Milestone steps created.