how can i obtain s curve

S
Shah. HB 👤 Member for 17 years 6 months

Hi to all



In the tools ,option , graphical reports there will be choices early & late, select which ever you need

P
PINAN T. 👤 Member for 18 years 10 months

use tabular report tabular





or use graphic report with labels

A
Angel Cruz 👤 Member for 16 years

how to set up S-curve in P3 obtaining Late Dates using tabular reports resouce loading?

R
Rafael Davila 👤 Member for 22 years 3 months

Yaser,



Because the metrics is meaningless it does not matter how you update, anyway it will still be nonsense. You can use a single resource a single activity that span the whole job duration, assign a predefined curve and you will get equally invalid measure with less effort, if this is the idea. With P3 you will get a meaningless S-Curve with early and late dates at the click of the mouse, at this P3 is so good that even meaningless is easy.



If you stick to PP in a few months you will be throwing dirty water at me, and both will laugh, believe me here you will get good at planning, keep asking here.



Best Regards,

Rafael

P
PINAN T. 👤 Member for 18 years 10 months

you want scurve without resource or cost?



if you are in a hurry atleast add one resource for all activities and make BQ EQ OD

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts