S-Curve

R
Ruel Camaquin 👤 Member for 17 years 7 months

Guys,



Thank you for the enlightment on the matter, now all i need is to convince my boss that it is not possible!



Cheers!



Ruel

J
joseph ador 👤 Member for 17 years 4 months

Ruel,



you can’t produce the S-curve or histogram without any resources assigned to the project activities. As you can see by following the steps given below, you are ask to check either you will show the s-curve/histogram based on units/cost of nonlabor. materials and labor assignments. Therefore it must be primarily comes from your resources assigned.



Regards,

Josh

R
Ruel Camaquin 👤 Member for 17 years 7 months

Guys,



Thanks for your quick response, but how about if you schedule if is just activity driven and do not have any resources?



Again thanks a lot guys!



Cheers!



Ruel

I
Irfan Khan 👤 Member for 16 years 11 months

Ruel,



U can generate S-Curve in P6. Just follow these steps:-



>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

> Go to View > Show on Bottom > Resource Usage Profile



> Select any one resource what u defined & u wanted to show in as a S-Curve



> Right Click on the open Space Area of Histogram.



>mark the Cumulative Box for Budgeted & Actual depending on your requirments.

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>



regards,,,,,










Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts