you cant produce the S-curve or histogram without any resources assigned to the project activities. As you can see by following the steps given below, you are ask to check either you will show the s-curve/histogram based on units/cost of nonlabor. materials and labor assignments. Therefore it must be primarily comes from your resources assigned.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Ruel,
Below link is a good approach if Project is Activity Driven. I explain 3 options that you can use.
Duration % Complete Post #3
Guys,
Thank you for the enlightment on the matter, now all i need is to convince my boss that it is not possible!
Cheers!
Ruel
Ruel,
you cant produce the S-curve or histogram without any resources assigned to the project activities. As you can see by following the steps given below, you are ask to check either you will show the s-curve/histogram based on units/cost of nonlabor. materials and labor assignments. Therefore it must be primarily comes from your resources assigned.
Regards,
Josh
Guys,
Thanks for your quick response, but how about if you schedule if is just activity driven and do not have any resources?
Again thanks a lot guys!
Cheers!
Ruel
Ruel,
U can generate S-Curve in P6. Just follow these steps:-
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
> Go to View > Show on Bottom > Resource Usage Profile
> Select any one resource what u defined & u wanted to show in as a S-Curve
> Right Click on the open Space Area of Histogram.
>mark the Cumulative Box for Budgeted & Actual depending on your requirments.
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
regards,,,,,
Click the link below to download the steps which is published on the other thread with same topic.
Step On How to Produce S-Curve & Histogram