No, you cannot maintain external relationship because it will have a new unique task ID assign in P6 Database even it will carry the same activity ID. You can only maintain relationship inside the WBS when copy. You can maintain external relationship if you move (not copy or cut) the WBS using drag & drop on the chart view.
Hi Rodel,
I want to maintain external relationship while pasting WBS from one project to another, if both the projects are project are having similar activity ID. Is it possible......Since while pasting a WBS, external relationship are not present......
Gobinath,
You can use WBS Window if copying WBS from EPS to another EPS.
If copying specific activity from EPS to another EPS then group and sort by EPS/WBS indent and all level option only.
Note: Make sure both EPS are open.
Rodel,
in project window, i can able to view the project titles only. is it possible to view wbs detail in project window.
because i need to copy some wbs titles and its activities to another EPS/Project.
Gobinath,
You can only do that in Project Window and not Activity Window because of the way it was organize or Group & Sort.
Alternatively on Project Window click the Chart icon and use copy and paste from one EPS to another EPS.
Hai Rodel,
i tried , its working within the EPS.
i cannot do in another EPS
shall u tell any other method
Be carefull, because the EPS activity codes will turn to Project activity code. If later you decide to copy or move the project back to the old EPS the codes used will be in the EPS activity code and in the Project activity code.
Gobinath,
Yes you can copy and paste Activities, WBS from one EPS to another EPS. (short cut: Ctrl+c to copy, Ctrl+v to paste).
Alternatively use drag and drop on chart view if cut and paste.