Dear Paul,
Thank you for your advice. I will post it again to the correct place. I have overlooked this matter.
At first, I have the same idea with you. Now, I believe the answer may not be so simple.
Best regards,
Billy
Welcome to PP Billy Hui,
I think you need to post this item in "Primavera Project Planner - P3" forum for a better selection of replies.
By way of an answer, if you are talking about allowing for activities to be interupted by unscheduled events during the progress of a project, in the Dates area of the Activities form you can suspend an activity that has been interupted by inserting a Suspend date and a Resume date.
Is this what you had in mind?
Paul