Schedule % Complete vs Activity % Complete
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
thanks to all.....
Irfan,
Their answers are all correct. Schedule % Complete is Baseline Planned % (if have baseline) or current Project Planned % Complete (if no baseline assigned) and Activity % Complete is Actual % complete.
The reason why it has 0% on summary bands is because you haven’t cost loaded your schedule. P6 calculation of Progress is based on cost.
It is the Planned Progress of the Baseline...if as per baseline the activity should have been completed...the Schedule Perent will show 100%. Thanks.
r
thanks All
i agree but y it is not showing in total bar...?
Hi
i am not sure but i think activity percent completion is actual progress
while schedule percent completion is the scheduled ( planned progress)
Alaa