Schedule % Complete vs Activity % Complete

I
Irfan Khan 👤 Member for 16 years 11 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Irfan,

Their answers are all correct. Schedule % Complete is Baseline Planned % (if have baseline) or current Project Planned % Complete (if no baseline assigned) and Activity % Complete is Actual % complete.



The reason why it has 0% on summary bands is because you haven’t cost loaded your schedule. P6 calculation of Progress is based on cost.

R
Rashid Iqbal 👤 Member for 16 years 2 months

It is the Planned Progress of the Baseline...if as per baseline the activity should have been completed...the ’Schedule Perent’ will show 100%. Thanks.



r

I
Irfan Khan 👤 Member for 16 years 11 months

thanks All



i agree but y it is not showing in total bar...?

A
Alaa Al haj 👤 Member for 18 years 7 months



Hi

i am not sure but i think activity percent completion is actual progress

while schedule percent completion is the scheduled ( planned progress)





Alaa

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts