I did not include status date as it mean to show the progress on bar and also not run the schedule to move all non-started and in progress activities to status date.
I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?
I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?
Use the % complete to progress your bar instead of Physical %.
Right click then select task information then under General Tab enter Percent Complete or Select Header Column then right click, select insert column then under field name select % complete. Once the % complete column is visible enter your progress.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Trevor,
I did not include status date as it mean to show the progress on bar and also not run the schedule to move all non-started and in progress activities to status date.
Rodel, in your tracking example, what date is the status date?
Thanks Rondel, i just needed to adjust my gantt chart wizard. thanks for your help!
Jaime,

As long as you progress your activity using % complete then even 100% should be doing the same. See sample below
Rodel,
Another quick query!
I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?
Thanks
Rodel,
Another quick query!
I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?
Thanks
Jaime,
Use the % complete to progress your bar instead of Physical %.
Right click then select task information then under General Tab enter Percent Complete or Select Header Column then right click, select insert column then under field name select % complete. Once the % complete column is visible enter your progress.