Activity Progressing!

Member for

19 years

Trevor,

I did not include status date as it mean to show the progress on bar and also not run the schedule to move all non-started and in progress activities to status date.

Member for

19 years 11 months

Rodel, in your tracking example, what date is the status date?

Member for

15 years 9 months

Thanks Rondel, i just needed to adjust my gantt chart wizard. thanks for your help!

Member for

19 years

Jaime,

As long as you progress your activity using % complete then even 100% should be doing the same. See sample below

MSP Sample Progress

Member for

15 years 9 months

Rodel,



Another quick query!



I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?



Thanks

Member for

15 years 9 months

Rodel,



Another quick query!



I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?



Thanks

Member for

19 years

Jaime,

Use the % complete to progress your bar instead of Physical %.

Right click then select task information then under General Tab enter Percent Complete or Select Header Column then right click, select insert column then under field name select % complete. Once the % complete column is visible enter your progress.