You might not have privilege to that field. To set privilege select Admin-> Security Profiles. Tick Project then locates Edit Resource Assignment for Resource Planning and make sure it has tick.
Is field remaining early units is present on the spreadsheet? What are your duration type settings? If fixed Units or Fixed Unit/Time then those setting are not updatable in spreadsheet but you can update them on the columns. Fixed Duration and Units or Fixed Duration and Unit/Time are only updatable settings on the spreadsheet.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Lucas,
Last check, are you using roles assignment as resource or resource itself? If roles make sure Edit Roles Assignment for Resource Planning also ticks.
Make sure that Remaining Early Units is display on the spreadsheet and not Remaining Early Cost.
It much easier if your profile is set to superadmin (less restriction)
I have checked and it is ticked.
Lucas,
You might not have privilege to that field. To set privilege select Admin-> Security Profiles. Tick Project then locates Edit Resource Assignment for Resource Planning and make sure it has tick.
Hi,
yes, it is present in the spreadsheet.
My duration setting is fixed duration and fixed unit. I check the help section and still cant solve it.
I can only make changes to the budgeted units, but not remaining unit and actual unit.
Kindly advice.
Regards
Lucas
Hi Lucas,
Is field remaining early units is present on the spreadsheet? What are your duration type settings? If fixed Units or Fixed Unit/Time then those setting are not updatable in spreadsheet but you can update them on the columns. Fixed Duration and Units or Fixed Duration and Unit/Time are only updatable settings on the spreadsheet.