Don’t use the assignment module and used activity module instead. Click the activity usage spreadsheet icon or select View->Show on Bottom-> Activity Usage Spreadsheet. On the bottom right screen, right click and select spreadsheet fields. Under Cost or Units you can select BL?? and actual fields that you wanted to show. If running a report don’t use resource & roles assignment and used activity instead. Click the column and under cost and unit select BL?? and actual fields to use.
Thanks Rodel. However, there’s no option to choose the baseline actual/budgeted units in resource spreadesheet windows. I even tried reports but to no avail. Basically we want the periodic comparison of quantities againts baseline.
You need to maintained and assigned the baseline first before you can select it. (It should be resource and cost loaded as per your actuals.) Or you can use current Project as a baseline.
If you want to show it on column select cost or unit then select BL? cost or unit. Or select Earned Value then select Plan & Actual (cost or unit)
If in activity usage spreadsheet, right click then select spreadsheet field then either cummulative or time interval select BL ??? (cost or unit) & Actual.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Don’t use the assignment module and used activity module instead. Click the activity usage spreadsheet icon or select View->Show on Bottom-> Activity Usage Spreadsheet. On the bottom right screen, right click and select spreadsheet fields. Under Cost or Units you can select BL?? and actual fields that you wanted to show. If running a report don’t use resource & roles assignment and used activity instead. Click the column and under cost and unit select BL?? and actual fields to use.
Thanks Rodel. However, there’s no option to choose the baseline actual/budgeted units in resource spreadesheet windows. I even tried reports but to no avail. Basically we want the periodic comparison of quantities againts baseline.
You need to maintained and assigned the baseline first before you can select it. (It should be resource and cost loaded as per your actuals.) Or you can use current Project as a baseline.
If you want to show it on column select cost or unit then select BL? cost or unit. Or select Earned Value then select Plan & Actual (cost or unit)
If in activity usage spreadsheet, right click then select spreadsheet field then either cummulative or time interval select BL ??? (cost or unit) & Actual.