Possible Global change

S
Salman Ahmed 👤 Member for 16 years 3 months

Thanks guys,



Is this Schedule % complete taken from the baseline’s activity % complete or baselines duration % complete.


A
Arnold Puy 👤 Member for 19 years 1 month

Hi Salman,



In addition to Ferdinand info, try The following:



1. Create a "Activities" as you User Defined Fields, (Weekly accomplishment) as your Title, and "Number" as your Data Type.

2. When done, create a new global change with parameters:



Where:

Activity Status "is not equal" Not Started



Then:

Weekly accomplishment " = " Activity % Complete - Schedule % Complete



HTH.



Regards,



Arnold

M
Mai Tawfeq 👤 Member for 16 years 3 months

please guys anyone can explain me what does mean global change and what the advantage can be by using it?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts