Thanks guys,
Is this Schedule % complete taken from the baselines activity % complete or baselines duration % complete.
Hi Salman,
In addition to Ferdinand info, try The following:
1. Create a "Activities" as you User Defined Fields, (Weekly accomplishment) as your Title, and "Number" as your Data Type.
2. When done, create a new global change with parameters:
Where:
Activity Status "is not equal" Not Started
Then:
Weekly accomplishment " = " Activity % Complete - Schedule % Complete
HTH.
Regards,
Arnold
please guys anyone can explain me what does mean global change and what the advantage can be by using it?
Try
UDF EQ Activity % complete - Schedule % COmplete