fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Dan,
you could record a macro which would use both the current date and the status date (in Project, Project Information) to define the Spotlight zone
these are the only user defined dates to be used to define an area on the screen
Alexandre
Hello Alexander,
Yes I know and it is a very god function that are missing in msp. I thougt maybe some one hade made a macro make this work.
//Dan
Dan,
spotlight does not exist in MSP
you could use the Task Range or Date Range filters instead, but it is not as useful as the spotlight
many P3 and P6 functionalities do not exist in MSP
Alexandre