Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2010-03-22 13:50 Permalink RE: Spotlight Dan, you could record a macro which would use both the current date and the status date (in Project, Project Information) to define the Spotlight zone these are the only user defined dates to be used to define an area on the screen Alexandre Member for 15 years 9 months Member for 15 years 9 months Submitted by Dan Mårtensson on Mon, 2010-03-22 10:30 Permalink RE: Spotlight Hello Alexander, Yes I know and it is a very god function that are missing in msp. I thougt maybe some one hade made a macro make this work. //Dan Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2010-03-20 08:01 Permalink RE: Spotlight Dan, spotlight does not exist in MSP you could use the Task Range or Date Range filters instead, but it is not as useful as the spotlight many P3 and P6 functionalities do not exist in MSP Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2010-03-22 13:50 Permalink RE: Spotlight Dan, you could record a macro which would use both the current date and the status date (in Project, Project Information) to define the Spotlight zone these are the only user defined dates to be used to define an area on the screen Alexandre
Member for 15 years 9 months Member for 15 years 9 months Submitted by Dan Mårtensson on Mon, 2010-03-22 10:30 Permalink RE: Spotlight Hello Alexander, Yes I know and it is a very god function that are missing in msp. I thougt maybe some one hade made a macro make this work. //Dan
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2010-03-20 08:01 Permalink RE: Spotlight Dan, spotlight does not exist in MSP you could use the Task Range or Date Range filters instead, but it is not as useful as the spotlight many P3 and P6 functionalities do not exist in MSP Alexandre
Member for
22 years 9 monthsRE: Spotlight
Dan,
you could record a macro which would use both the current date and the status date (in Project, Project Information) to define the Spotlight zone
these are the only user defined dates to be used to define an area on the screen
Alexandre
Member for
15 years 9 monthsRE: Spotlight
Hello Alexander,
Yes I know and it is a very god function that are missing in msp. I thougt maybe some one hade made a macro make this work.
//Dan
Member for
22 years 9 monthsRE: Spotlight
Dan,
spotlight does not exist in MSP
you could use the Task Range or Date Range filters instead, but it is not as useful as the spotlight
many P3 and P6 functionalities do not exist in MSP
Alexandre