progress against critical path

M
mukunda y 👤 Member for 17 years 6 months
S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Mukunda,



The Schedule is a live document. The approved Schedule is your baseline. This is what you measure your progress against. You do not measure the progress against the critical path. Critical Path are activities with float zero or negative (later on).



Each day the float on your activities decreases. So if you don’t complete the activity, and the float is gone, it becomes critical.



With kind regards,



Samer

M
mukunda y 👤 Member for 17 years 6 months

is it practical? anybody measuring progress by this method?

A
Anoon Iimos 👤 Member for 19 years 8 months

critical path only changes once you make updates, just don’t forget to keep the baseline

A
Anoon Iimos 👤 Member for 19 years 8 months

try to create filter to show only the critical path, and then make updates

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts