Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?
this indeed a FAQ! it is only possible to roll up resource names by writing a macro
however, I would not roll up my resource names in the Resource Name column, as it would duplicate the resource workload at work package (summary task) level; if necessary, use a custom text field instead
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
MAYBE THIS IS WHAT YOU ARE LOOKING FOR.

Format the bar chart portion of a Gantt view:
http://office.microsoft.com/en-us/project/HA012253681033.aspx
Go to Display task names for individual .......
Have some issues with overlapping tasks, unless can be fully resolved I would avoid using this at all.
Hope this helps.
R. Davila
Neil,
I remember having seen such a macro a few years ago, but I do not know were; thats too bad!
Have a look at the MSP newsgroups
Alexandre
Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?
Thanks
Neil,
this indeed a FAQ! it is only possible to roll up resource names by writing a macro
however, I would not roll up my resource names in the Resource Name column, as it would duplicate the resource workload at work package (summary task) level; if necessary, use a custom text field instead
Alexandre