PLST and PLFN are the Start and Finish Dates of an updated program.
If u want new dates to compare ur actual dates, then u can assign target program by going to Tools-> Project Utilities -> Targets and then select the program.
The target and current program shud b in same folder.
I no longer have P3 but these fields are Date Fields, zero is a number so either you set your global changes to a specific date or to an empty value. If you have access to the field then try setting your global changes equal to ’’ or ’’’’ , using single quotations or double quotations with no space in between, if not then try with aspace in between and see if you can hit the change you are looking for.
Also if progress is reported on several activities it might be the field is locked for editing, though not sure.
In Primavera SureTrak there is an alternate method, maybe P3 has a similar procedure:
Delete target dates
1 Choose Define, Target Dates.
2 Choose the All Activities option.
If the project layout is filtered, the activities excluded from the layout filter are unaffected. Hidden activities are also unaffected.
3 Click Clear Targets.
4 Indicate that you want to clear the target dates.
Tip
To delete target dates for selected activities, choose the Selected Activities option, then clear the target dates for those activities.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
hi Atif,
PLST and PLFN are the Start and Finish Dates of an updated program.
If u want new dates to compare ur actual dates, then u can assign target program by going to Tools-> Project Utilities -> Targets and then select the program.
The target and current program shud b in same folder.
PLST and PLFN cant be changed.
Cheers,
Atif,
I no longer have P3 but these fields are Date Fields, zero is a number so either you set your global changes to a specific date or to an empty value. If you have access to the field then try setting your global changes equal to ’’ or ’’’’ , using single quotations or double quotations with no space in between, if not then try with aspace in between and see if you can hit the change you are looking for.
Also if progress is reported on several activities it might be the field is locked for editing, though not sure.
In Primavera SureTrak there is an alternate method, maybe P3 has a similar procedure:
Delete target dates
1 Choose Define, Target Dates.
2 Choose the All Activities option.
If the project layout is filtered, the activities excluded from the layout filter are unaffected. Hidden activities are also unaffected.
3 Click Clear Targets.
4 Indicate that you want to clear the target dates.
Tip
To delete target dates for selected activities, choose the Selected Activities option, then clear the target dates for those activities.
Best regard,
Rafael