Thanks Ronald;
I selected Activity Duration Type (on the General Tab) to “Fixed Units” and it worked.
Best Regards,
Abeer
In P6, the activity duration, resource quantity, and resource rate are always balanced. To fix the activity duration and the quantity (budget), then it is necessary to set Activity Duration Type (on the General Tab) to “Fixed Duration & Units” and let the rate change as needed. Good luck!