Hi Tim
I assume that your projects are in P6 and to hear from salesmen that other products are so much better doesn’t help you for your current task.
1100 projects shouldn’t be a problem but please explain what you mean by variety of planned dates?
Regards
Dieter
Hi Tim
Go and look at astadev.com to see what Powerproject can do.
I have been using it for the last 18 years.
Also go and see how many problems are logged on the Asta PP thread as against the primavera threads. 100 - 1 against I would suggest.
Vladimir and Rafael will pitch for the Russian product called Spider but i prefer to work with something that is used by most operators in the UK.
Best regards
Mike Testro
What is Powerproject Enterprise?
Hi Tim
In Powerproject enterprise I would select all 1100 projects - put them uner 1 summary bar and drag that top bar to the left by one week and then flag it to start then.
I know nothing about P6 but if you cant do that then it confirms my suspiscions - it is a crap peice of software.
Best regards
Mike Testro
Im talking about 1100 projects with an infinite variety of planned starts.
View "Projects" --> Modify the utmost project --> mark all you want to move --> click into the column "Planned Start" --> "Fill Down"