Shifting the Planned Start of Multiple projects.

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Tim



I assume that your projects are in P6 and to hear from salesmen that other products are so much better doesn’t help you for your current task.

1100 projects shouldn’t be a problem but please explain what you mean by variety of planned dates?



Regards



Dieter

M
Mike Testro 👤 Member for 20 years 6 months

Hi Tim



Go and look at astadev.com to see what Powerproject can do.



I have been using it for the last 18 years.



Also go and see how many problems are logged on the Asta PP thread as against the primavera threads. 100 - 1 against I would suggest.



Vladimir and Rafael will pitch for the Russian product called Spider but i prefer to work with something that is used by most operators in the UK.



Best regards



Mike Testro

M
Mike Testro 👤 Member for 20 years 6 months

Hi Tim



In Powerproject enterprise I would select all 1100 projects - put them uner 1 summary bar and drag that top bar to the left by one week and then flag it to start then.



I know nothing about P6 but if you can’t do that then it confirms my suspiscions - it is a crap peice of software.



Best regards



Mike Testro

T
Tim Breeding 👤 Member for 17 years 1 month

I’m talking about 1100 projects with an infinite variety of planned starts.

D
Dieter Wambach 👤 Member for 19 years 5 months

View "Projects" --> Modify the utmost project --> mark all you want to move --> click into the column "Planned Start" --> "Fill Down"

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts