Thanks All
i change the default Global Calendar to match the project Calendar
and now it is ok
i don’t know what will we do without the best planner around the world on this Forum
thanks again
we should be proud of this Forum
yours
Alaa
Hi Neil,
You are right..
Its okey..
Regards,
Arnold
*Arnold
Sorry Arnie! :-)
Alaa,
This has always been an issue with P6, upto 6.2, and as Arniold states, v7 has its own time periods to correct this problem.
However, on versions prior to this, set your durations to hours and the issue will be resolved.
Regards,
Walshy
Hi Alaa,
Try to use WBS Summary as activity type for each WBS level or to the highest level.
With P6 v7, each calendar has its own "Time Periods" so you don’t have to worry.
Regards,
Arnold
at summary level, P6 uses global calendat to calculate duration.
Global calendar and project calendar need to be same to show matching figures
please check your global calendar