WBS- SUMMARY DURATION

A
Alaa Al haj 👤 Member for 18 years 7 months
A
Alaa Al haj 👤 Member for 18 years 7 months



Thanks All

i change the default Global Calendar to match the project Calendar

and now it is ok

i don’t know what will we do without the best planner around the world on this Forum



thanks again

we should be proud of this Forum





yours

Alaa

N
Neal Walsh 👤 Member for 18 years 9 months

Alaa,



This has always been an issue with P6, upto 6.2, and as Arniold states, v7 has its own time periods to correct this problem.

However, on versions prior to this, set your durations to hours and the issue will be resolved.



Regards,



Walshy

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Alaa,



Try to use WBS Summary as activity type for each WBS level or to the highest level.



With P6 v7, each calendar has its own "Time Periods" so you don’t have to worry.



Regards,



Arnold

A
A D 👤 Member for 19 years 1 month

at summary level, P6 uses global calendat to calculate duration.



Global calendar and project calendar need to be same to show matching figures

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts