BUDGET UNITS OVERRIDE ACTUAL UNITS W/ACTUAL FINISH
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Jeremy,
I probably have more experience than all of them put together! And that goes for quite a few guys on this forum.
Thanks - Youve done what our Primavera Rep. and Primavera help line could not do. That was very frustrating for our guys in the field and for me. -Rookie eh-
JC
Set the activity to "auto compute actuals"
Set the resource to "auto compute actuals"
and there is another one, but I am having a "senior moment", I shall fire P6 up and refresh
David - Thank you. When you say loads of other ways, How else can it be done?
Thanks again
JC
Loads of places you can make it do that!!!!
In the project tab, check under the "Calculations" tab that "recalculate actual unist an cost when duration % complete changes" is NOT checked.