BUDGET UNITS OVERRIDE ACTUAL UNITS W/ACTUAL FINISH

D
David Kelly 👤 Member for 21 years 8 months

Jeremy,



I probably have more experience than all of them put together! And that goes for quite a few guys on this forum.


J
JEREMY CORNER 👤 Member for 16 years 7 months

Thanks - You’ve done what our Primavera Rep. and Primavera help line could not do. That was very frustrating for our guys in the field and for me. -Rookie eh-

JC

D
David Kelly 👤 Member for 21 years 8 months



Set the activity to "auto compute actuals"



Set the resource to "auto compute actuals"





and there is another one, but I am having a "senior moment", I shall fire P6 up and refresh

J
JEREMY CORNER 👤 Member for 16 years 7 months

David - Thank you. When you say loads of other ways, How else can it be done?

Thanks again

JC

D
David Kelly 👤 Member for 21 years 8 months

Loads of places you can make it do that!!!!



In the project tab, check under the "Calculations" tab that "recalculate actual unist an cost when duration % complete changes" is NOT checked.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts