I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.
This can be done by
1.Format - organize - Select activity data item - then remove all items under heading group by
2.Under sort by - selct early start or early finish - order by ascend or descend
3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)
This will give you all critical activities listed one after the other.
Im not sure whether this is what you are looking for.
Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Vishnu...sorry but the requeriment was ask to me bad...the people that ask it only need the S-curve but they have a wrong idea.
thanks
Hi Orozco,
I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.
This can be done by
1.Format - organize - Select activity data item - then remove all items under heading group by
2.Under sort by - selct early start or early finish - order by ascend or descend
3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)
This will give you all critical activities listed one after the other.
Im not sure whether this is what you are looking for.
Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance