Critical Path - Graph like S-Curve

J
Jhorbam Baena Orozco 👤 Member for 16 years 10 months

Hi Vishnu...sorry but the requeriment was ask to me bad...the people that ask it only need the S-curve but they have a wrong idea.



thanks

S
Sreejish Vishnu 👤 Member for 20 years 8 months

Hi Orozco,



I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.



This can be done by

1.Format - organize - Select activity data item - then remove all items under heading ’group by’

2.Under sort by - selct early start or early finish - order by ascend or descend



3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)



This will give you all critical activities listed one after the other.



I’m not sure whether this is what you are looking for.

S
Shah. HB 👤 Member for 17 years 8 months

Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts