Hi Izam,
You must have cost loaded in your programme. Besides, "Physical % Complete" doesnt roll-up in the summary band, but there is a workaround.
Try to convert your Budgeted Units into Cost by just assigning Price/Unit to the Resource.
Likewise,there is a workaround to convert your "Physical % Complete" into "Performance % Complete" and will roll-up in the Activity & WBS Windows If you have assign Cost to your Task.
Regards,
Arnold
Arnold
Mine was budgeted units loaded. Do you have any idea?
Hi Izam,
Your schedule is a resource cost loaded?
Regards,
Arnold
Hi Izam,
Physical % complete will not roll up to WBS summary,my advice is do on excel manually.Try to use Duration&Units percent complete,it will roll up to WBS summary.
I hope it will help...
Best regards,